Clinic Progress Pics

June 27, 2012

These pics show the progress of our strawbale house and clinic from the beginning to, well, now.

Dsc_6048

 

 

 

 

 

 

Fall 2010 - Land purchased at 450 Bay St. Orillia

Dsc_7428

 

 

 

 

 

 

January 2012 - ICF foundation poured and framing started - boy did I freeze my fingers

Dsc_7552

 

 

 

 

 

 

February 2012 - Framing almost complete

Dsc_7793

 

 

 

 

 

 

March 2012 - Roof is up, dormers built

Dsc_7958

 

 

 

 

 

 

April 2012 - Windows in, scaffolding up and ready for strawbales. 650 Bales were delivered to our driveway - that took 7 of us about 1 hour to move inside to protect from the rain.

Dsc_8109

 

 

 

 

 

 

Here's what the walls look like in my office before plastering

Dsc_8135

 

 

 

 

 

 

May 2012 - Here's what they look like in the reception area after plastering

Dsc_8169

 

 

 

 

 

 

June 2012 - Plastering complete, soffits and siding almost finished

Dsc_8195

 

 

 

 

 

 

June 2012 - Here is where we are at as of last Friday. Good thing our roof is on, we've had some torrential downpours.